To schedule the docking job items:
- Click Docking.
- Select the docking project you wish to schedule jobs for.
- Click Docking time line.
(To the left all job items are listen vertically, and the days/weeks/months are represented horizontally.)
- You can change the scale for the timeline using the [Zoom in] and [Zoom out] buttons found in the top menu or using the selector next to them.
The yellow vertical line represents today. If you have set a start date for any of your job items, they will appear in the timeline view, and if you have also set a value in duration for it the job items will be represented as a line stretching along the time line. These settings are found at the bottom on each job item.
Note: The actual start date for a dry dock project may change several times during the planning of the project. By setting a job item’s start date as “Relative to dock date”, the job item’s start date will be updated, automatically when the entire project date is changed.
- You can edit the start date and the duration in this time line view, by clicking “Edit in grid”.
- Click and hold on the center of a job line and drag the job item to a new date.
- If you click and hold at either the front or end of the line, you can adjust the duration for the job.
- Double clicking a job line, will open the job item, and you can edit its details.
The colour on the job lines represents the job items status.
Blue: Planned
Red: Overdue (or not started (no progress % for the job item has been set)
Purple: In progress (a % progress has been set for the item)
Green: Signed out.
Tip: If you have made changes to a job item, but this is not reflected in the time view, click Refresh to update the view.